Odisha Approves ₹54,288 Crore Power and Renewable Energy Projects
At a glance
- Odisha HLCA approved ₹54,288 crore in power and renewable energy projects.
- Two thermal power plants and two hydropower projects were cleared.
- Approval took place at the 46th HLCA meeting chaired by Chief Minister Majhi.
The Odisha High-Level Clearance Authority (HLCA) gave approval to a set of power and renewable energy projects valued at over ₹54,000 crore on September 23, 2026. This decision was made during the authority’s 46th meeting, which was chaired by Chief Minister Mohan Charan Majhi.
The projects approved include two thermal power plants and two pumped-storage hydropower projects. The thermal plants, located in Deogarh and Angul, were secured by NLC India Ltd and together represent an investment exceeding ₹46,000 crore.
The hydropower projects are planned for Rayagada and Koraput districts. In total, the HLCA approved 27 projects across 15 districts, with the power and renewable energy sector accounting for a substantial portion of the total investment.
According to Energetica India Magazine, the combined investment for the four approved power and renewable energy projects reached ₹54,287.70 crore. The magazine reported that these projects were distributed across 15 districts in Odisha.
What the numbers show
- ₹54,288 crore was allocated to power and renewable energy projects.
- Two thermal power plants will add a combined 4,280 MW of capacity.
- The total investment approved for all 27 projects was ₹2,47,115.70 crore.
The HLCA’s 46th meeting marked a major round of project clearances, with the energy sector forming a key part of the investment portfolio. The approval process included both traditional thermal and renewable hydropower developments.
NLC India Ltd secured both thermal power projects, which are expected to be developed in Deogarh and Angul districts. The pumped-storage hydropower projects, meanwhile, are set for Rayagada and Koraput, further diversifying Odisha’s energy infrastructure.
Energetica India Magazine confirmed the approval of four power and renewable energy projects at the HLCA meeting chaired by Chief Minister Mohan Charan Majhi. The approvals were part of a broader set of clearances for projects in multiple districts.
* This article is based on publicly available information at the time of writing.