NESO Issues Electricity Margin Notices for Fourth Day

Great Britain’s National Energy System Operator issued two electricity margin notices on Friday, November 27, 2026, bringing the run of daily notices to four days, according to ITV. Notices had also been issued on each day from Tuesday, November 24.

NESO describes the notice as a signal to the electricity market requesting more available supply relative to predicted demand. Its general explanation says issuing a notice does not, on its own, establish that demand cannot be supplied or that customers’ electricity is at risk.

For the November 27 notices, a NESO spokesperson said customers did not need to take action and their supplies were not at risk, according to ITV. The spokesperson also said the notices did not constitute a power-cut warning.

In its November 27 National Electricity Transmission System status report, NESO assigned yellow forecast-risk ratings to three categories: system margins, active constraints and system warning. Those ratings covered the next 24 hours. For November 27, the document recorded 14,148 MW as the minimum de-rated margin. It also entered 6,708 MW under total balancing-mechanism spend for the previous 24 hours.

Electricity purchases through auctions on interconnectors involving Belgium, France and the Netherlands reached 1.8 GW per hour on Friday morning, according to ThePrint’s account of NESO’s procurement. The report put the clearing price for some of those transactions at approximately £400 per MWh.

For UK gas-fired generation, ThePrint cited figures from energy consultancy LCP Delta showing that plants accepted offers exceeding £600 per MWh on Friday morning. Its account also put prices during Thursday evening’s tighter conditions, on November 26, at almost £1,700 per MWh.