Ofgem Consults on Bacton Redevelopment Funding

Ofgem is consulting on a proposed £140.37 million allowance for National Gas Transmission’s Bacton Gas Terminal redevelopment, with the scope of work retained but funding below the amount requested. The consultation opened on 27 November 2026 and sets out the regulator’s provisional position ahead of a final decision.

The proposed allowance is 19% below National Gas Transmission’s £173.94 million request, according to the consultation. Both figures use 2018-19 prices. The company’s re-opener application was submitted in October 2024, with an update in March 2026.

Under Ofgem’s proposal, the work would cover the condition of the terminal’s cathodic protection system, actuators and critical valves, alongside control, instrumentation and low-voltage assets. Inspection and cleaning of two major pipelines are also described in the consultation.

Ofgem describes Bacton as linking Great Britain’s National Transmission System with supplies from the North Sea, interconnectors to Europe and the wider domestic network. These connections allow gas to move both into and out of the terminal.

The regulator said its proposed funding reductions relate mainly to its assessment of allowances for risk and contingency, together with company costs classified as direct and indirect. In Ofgem’s assessment, the evidence supplied so far does not justify the full sums requested. The consultation invites additional evidence that could alter that provisional assessment.

For delivery, the consultation proposes completion in March 2035. It also proposes a Price Control Deliverable through which outputs would be monitored and funding returned if agreed outputs were not delivered. Ofgem said the company should arrange the work to accommodate customer and network requirements while maintaining Bacton’s resilience.

The detailed-cost stage followed Ofgem’s August 2024 approval of Option 1, named Base Case Asset Health, as its preferred option for the re-opener’s second stage. That option covered work on asset condition through 2035, while leaving open the possibility of rationalisation at a later stage.

According to the consultation timetable, responses are due by 15 January 2027. Ofgem plans to publish responses after review on 1 March 2027, with a decision and direction planned for spring 2027.